DIESEL ENGINE STARTUP CHECKLIST
Diesel Engine environment and services
Pre commissioning work & checklist complete
Surroundings clean & clear from obstruction
Lighting/heating, etc., systems operational
Observations
Safety Checks
Ensure starting is inhibited until start-up is required
Set clean and fully assembled
No loose materials near set
Air ducts clear and clean
Access & egress routes unobstructed & labeled
Control & maintenance positions unobstructed
Room secure - no unauthorized access
Personnel warned of start-up process
Cooling System
Cooling water pipe work checked for leaks
Cooling water pump belts & guards checked for security / slipping
Coolant heater operational if provided
Cooling water is with added scale and corrosion inhibitors check
Cooling water level & valves open
Fans, pumps and controls checked
Secondary cooling system checked
Record dosing chemical & concentration
Diesel Fuel System
Bulk storage facility
Isolating valves correctly positioned
Transfer pumps & controls operational
Pipeline/tank heating system operational
Fill point alarm operational
Leaks check
Storage facility secure
Day tank Isolating and solenoid valves checked
Tank filled
Spillage containment & alarms operational
Transfer pump operational
Leak check
Fire valves & release tested and operational
Fire alarm/suppression system
Fire alarm/suppression system operational
Suppression system lock-off operational
Operator instructed in fire system operation
Lubrication system
Engine oil pan filled to correct level
Oil make up system operational
Starting system
Battery starting
Batteries installed, filled and connected
Battery charger commissioned
Isolating valves correctly positioned
Condensate drained
Exhaust system
Check security of pipe work & muffler
Check cowl and/or rain cap are operational
Check water drain pipe work and valves correct
Leak check
Check for exhaust gas recirculation
Ventilation & attenuation
Check louvers are clear and operational
Forced ventilation system operational if applicable
Check for hot air recirculation
Initial start-up
Manual start-up, idle & full speed checks complete
Local stop/emergency stop control checked
Remote start/stop/emergency stop checked
Checklist Completed by 
(Name & Signature)